Actual Achievement
DCM Homac Sapporo Product Center New Construction
- Client
- DCM Homac Co., Ltd.
- Planning site
- 5 Chome Kitakashiwagichō Eniwa-shi, Hokkaidō 061-1433
- Site area
- 28,906.44㎡(8,744.19坪)
- Construction area
- 15,873.95㎡(4,801.86坪)
- Total floor area
- 30,727.07㎡(9,294.23坪)
- Use
- Warehouse
- Structure and Scale
- 2 story Steel structure
- Construction period
- July 2016 - Aug. 2017
F&P`s Role
This project is total management project covering master planning to basic designing, contractor selection support, implementation design and supervision construction.
This warehouse is build to compensate for the expanding chain stores needs. Also implementing the newest material handling machines run by the newest WMS(Warehouse Management System) system will improve efficiency and satisfy the growing needs of Homac.