“Yamato Transport Co., Ltd., Narita Branch” construction has completed.
Completion ceremony of “Yamato Transport Co., Ltd., Narita Branch” , which F&P provided master plan and design/supervision was held on March 28.
This project is a reconstruction project of intensive facility for delivery service center in Narita area, which was planned in existing facility location consolidating surrounding facilities.
The site is located in about 4km away from Narita Interchange (IC) and Shinkuko IC of Shinkuko Expressway, adjacent to east side of Narita International Airport, which makes the location suitable for domestic and international delivery. In the future, a new IC is planned to be constructed nearby with the extension plan of Metropolitan Inter-City Expressway which will enhance the convenience of the area.
The building exterior is made with well-designed and easily maintained horizontal metallic insulation panel and the office area is made with insulated sash and dual folded insulation plate which improved the comfortability of the employers with simple design and high insulation.
We hope this facility will contribute to the social infrastructure and to the development of the community.
Construction Summary
Client | Yamato Transport Co., Ltd. |
---|---|
Planned Site | 155-2 etc., Chuou, Tenjinmine, Narita-shi, Chiba-ken | Site Area | 22,480.18㎡ |
Building Area | 5,924.23㎡ |
Total Floor Area | 9,305.35㎡ |
Usage | distribution center |
Structure and Scale | steel structure, partially reinforced concrete, 2F | Construction Period | 1 June, 2017 – 31 March, 2018 |
Photo by:Kawasumi・Kobayashi Kenji Photograph Office |