The opening ceremony of GLP Japan Inc.’s “GLP Hayashima Ⅲ(tentative name)” was held.
The opening ceremony of GLP Japan Inc.’s “GLP Hayashima Ⅲ(tentative name)”, which F&P provided design supervision service, was held on December 8, 2023.
The facility is located about 1.9km from “Hayashima IC” in Hayashima-cho, Tsukubo-gun, adjacent to Okayama City, and is one corner of a series of logistics facilities. As a hub base in the Mid-Shikoku area, this location has a high potential to help resolve the 2024 problem. This facility is a BTS type dedicated facility with Ryobi Transport Company as the tenant, which is the logistics division of Ryobi Holdings Co., Ltd.
F&P have been engaged in design supervision from the basic design phase of this project.
This project has a facility that emphasizes the efficiency of customer operations and the comfortable working environment for employees, including the installation of low-floor and high-floor berths and the installation of air conditioning in warehouses.
We will continue to take charge of construction supervision and will promote the creation of safe, high-quality logistics facilities with a view to completing construction in January 2025.
Construction Summary
Client | GLP Japan Inc. (GLP Hayashima Logistic Tokutei Mokuteki Kaisha) |
---|---|
Planned Site | 4775, Aza-Hataoka, Hayashima, Hayashima-cho, Tsukubo-gun, Okayama |
Site Area | Approx. 11,000㎡ | Total Floor Area | Approx. 18,000㎡ |
Usage | Commercial Warehouse |
Structure and Scale | Steel structure, 3-Story | Construction Period | December 2023 to the end of January 2025 (planned) |