The construction of Prologis Park Inagawa 2 was completed.

2021/09/02

The completion ceremony for Prologis’ Prologis Park Inagawa 2, which F&P provided construction supervision service, was held on August 26.

  

This project was promoted by the public and private sectors as the Inagawa Industrial Base Area Development Project. The facility is located 2km from the Kawanishi IC on the Shin Meishin Expressway and is located in a favorable location that not only accesses to Osaka and Kobe, but also provides access to various parts of western Japan from Kyoto to Hiroshima. The site is aimed at building a lively city close to a residential area with a large working population.

F&P took charge of construction supervision and supported the promotion of the project by checking the progress of the process, checking various plans and construction drawings, and confirming the quality of the project on-site.

The facility is a five-story, earthquake-resistant multi-tenant facility. A double ramp way structure allows trailers to approach each floor. The facility have common rest area and retail outlets on the fifth floor, giving consideration to the comfortable working environment for the employees. The construction work was carried out under the corona, crisis, and not only anti-corona measures are being implemented during construction, but also measures for corona are being considered for the facilities.
The project was integrated with the “Prologies Park Inagawa 1”, which is under construction in the neighboring area. Therefore, various information was shared, and the design, quality, BCP measures, and environmental measures were unified.

We hope that this facility will contribute to the development of the surrounding area and to the business development of business owners and customers.
 

Construction Summary

Client Prologis, Inc.
Planned Site 101-2 Kotani, Sashikuumi Aza Odani, Inagawa-cho, Kawabe-gun, Hyogo
Site Area 85,362.64㎡
Building Area 33,174.40㎡ (including attached building) 
Total Floor Area 158,644.29㎡ (including attached building) 
Usage Warehouse engaged in warehouse business
Structure and Scale Steel frame, 5F
Construction Period June 2020 to August 2021