The completion ceremony of Nippon Steel Kowa Real Estate Co., Ltd.’s “LOGIFRONT Koshigaya II ” was held.

2020/04/02

 The completion ceremony of Nippon Steel Kowa Real Estate Co., Ltd.’s “LOGIFRONT Koshigaya II ”, which F&P conducted design and supervision service, was held on March 2.

  

 This is the second project in the Kanto area under the logistics facility brand “LOGIFRONT” of Nippon Steel Kowa Real Estate Co. Ltd. and is planned as a BTS-type logistics facility for predetermined tenants.

 F&P provided planning support service to Nippon Steel Kowa Real Estate Co., Ltd. from the land selection phase, and then implemented tenant leasing, design service, and construction supervision service totally supporting this project.

 This project site is located about 6 km from the Soka Interchange on the Tokyo Outer Ring Expressway, within a 25 km from the center of Highway 16 and has good access to Highway 4. Therefore, it is a highly convenient location for selecting delivery routes to the consuming regions in Tokyo and Saitama prefectures depending on the traffic congestion situation.

 This facility is a BTS type logistics facility with a total floor area of about 27,000㎡. The facility is a four-story BOX type facility with truck berths on the first floor. The facility also meets the needs of tenants by installing a large eave on a part of the front of the truck berth.
 F&P is also trying to create a brand-name image by unifying the design with LOGIFRONT Koshigaya I, which is already in operation. Furthermore, plantings were set on the outer periphery of the site, in order to achieve harmony with the surrounding environment.

 F&P hopes this facility function as a party of social infrastructure and contribute to the business development of Nippon Steel Kowa Real Estate and the tenants.


Construction Summary

Client Nippon Steel Kowa Real Estate Co., Ltd. 
Planned Site 3092-1, Nishikata, Koshigaya-shi, Saitama
Site Area 13,348.20 ㎡  
Building Area 6,979.98 ㎡
Total Floor Area 27,024.04 ㎡
Usage Warehouse engaged in warehousing business
Structure and Scale Steel structure, 4F
Construction Period Month end of January 2019 to Month End of February 2020 (13 months)