The groundbreaking ceremony of Aeon Hokkaido Co., Ltd.’s “AEON Ishikari Center (tentative name)” was held.

2020/03/27

  The groundbreaking ceremony for the Aeon Hokkaido Co., Ltd.’s “AEON Ishikari Center (tentative name)”, which F&P provides project management, was held on March 26.

  

This is a facility that has been installed in the Process Center, which is responsible for the manufacture of the products, combined with a distribution hub for low-temperature distribution in Hokkaido, including the delivery of the manufactured products.

 As part of the project management, F&P conducted basic planning and design supervision, executing the project. 

 F&P were able to compile complex line plans, equipment plans, and operation plans as facilities that can function as distribution centers that can integrate goods procurement, manufacturing, and distribution operations with a view of future expansion. In addition, the plant is equipped with a normal power generation system using two 700 KW gas engines and a facility compatible with BCP, such as the diversification of water supply sources.

 Aiming to complete construction by the end of May 2021, F&P will contribute to the completion of high-quality facility as a major facility that combines Aeon Hokkaido’s food production center with a low-temperature distribution center.


Construction Summary

Client Aeon Hokkaido Co., Ltd.    
Planned Site 2-chome, Shinko Minami, Ishikari City, Hokkaido
Site Area 121,636.33㎡
Building Area 17,886.45㎡
Total Floor Area 27,559.80㎡
Usage Warehouses not engaged in factory or warehousing business
Structure & Scale 2F, Steel structure
Construction Period March 26, 2020 ~ May 31, 2021