The completion ceremony of Nippon Prologis REIT, Inc.’s “Prologis Park Iwanuma” was held.
The completion ceremony of Nippon Prologis REIT, Inc.’s “Prologis Park Iwanuma”, which F&P conducted design and construction supervision, was held on May 11, 2022.
The facility is a logistics warehouse with high disaster prevention measures, for the reasons that it experienced flood damage from the tsunami caused by the Great East Japan Earthquake in March 2011 and a massive fire in April 2020.
F&P provided design and construction supervision for the project.
This project is planned with the first floor at KBM+3.1m (flood level KBM+2.6m) based on lessons learned from the flooding caused by the Great East Japan Earthquake. In addition, based on lessons learned from a massive fire, a balcony is installed on the north side of the second floor to assist firefighting activities, and sprinklers are voluntarily installed in areas not facing exterior walls.
F&P hopes that this facility will respond to various needs and contribute to the business development of business owners and customers.
Construction Summary
Client | Nippon Prologis REIT, Inc. |
---|---|
Planed Site | 3-2-35, 2-28, 2-41, Kukominami, Iwanuma-shi, Miyagi |
Site Area | 45,704.77㎡ |
Building Area | 25,754.31㎡ |
Total Floor Area | 51,120.46㎡ |
Usage | Commercial warehouse |
Structure and Scale | S, 2-story |
Construction Period | March 1, 2021 to April 28, 2022 |